Rate cases tied to data centers: 63 tracked in 25 states

These are the rate cases, tariffs and contracts on this site where the filing itself ties the request to data center load. Being on this list does not mean households pay more: several of these cases exist specifically to make the data center pay its own way instead.

Pending

2
Pending Base rate case

This is Evergy's opening ask for its Kansas City area customers; the company already cut it once because of new data center revenue, and the case is now in its evidentiary hearing with no decision yet.

+$18a month
3
Pending Base rate case

As filed, a typical residential bill would rise about 13 dollars a month in 2027 and 8 to 9 dollars more in 2028, a combined 16.3 percent, but how much of that is really tied to data centers versus other grid needs is one of the contested questions in the case.

+$13a month
4
Pending Base rate case

This new Ameren Missouri request follows closely on the heels of the case approved in April 2025; nothing has been decided yet.

+$13a month
5
2027 electric rate case DTE Electric, MI
Pending Base rate case

If approved as filed, this would be a bigger increase than the 4.1 percent DTE got approved in its last case; MPSC Staff and the state Attorney General both want the increase cut well below what DTE asked for.

+$12a month, est.
6
Pending Rate matter, gas

Oglethorpe Power, which generates most of the electricity Georgia's EMCs sell, is adding natural gas plants it ties to data center and industrial load. EMC rates are set by each cooperative's board, not the Public Service Commission, so watch your EMC's rate notices.

no figure yet
7
Pending Rate matter

MEAG Power supplies the city owned utilities and expects data center load on its system to roughly double within about five years. City utility rates are set by each city, not the Public Service Commission.

no figure yet
8
Pending Rate matter, gas Hearing Dec 16

This case, still open as of August 2026, will help decide whether seven new gas plants built mainly for one company's data center get repaid entirely by that company or partly by everyday Entergy Louisiana customers. A commission decision was reportedly expected around December 2026, though that timeline was not confirmed by the commission itself.

no figure yet
9
2026 resource plan and large load contract NV Energy (Nevada Power), NV
Pending Rate matter

Nothing here changes a bill today. What matters is whether the large load contract survives intact; if it is weakened, the cost of plants built for data centers starts showing up in the next general rate cases around 2027 and 2028.

no figure yet
10
Pending Statewide

Transmission upgrades like this are typically billed to every electric customer in the state through transmission charges, not just to the data center that made the new line necessary, which is why the cost allocation question matters for ordinary bills even outside the counties involved.

no figure yet
11
MGE Very Large Customer tariff filing Madison Gas and Electric, WI
Pending Rider or surcharge

Nothing changes on home bills unless and until this tariff is approved, but its purpose is to keep future data center grid costs off residential rates.

no figure yet
12
Pending Rate matter

If regulators approve it, Oracle would cover part of We Energies' nuclear power costs instead of spreading them to all customers, which the company says will lower everyone's fuel charges rather than raise them.

no figure yet
13
Pending Base rate case

This is a proposed decrease, not an increase; I&M says new large industrial and data center customers are helping pay for the grid, letting it lower rates for everyone else, but the case still needs IURC approval.

-$7a month, est.

Decided and other matters

Approved Statewide From Jan 2027

This is new state law aimed at keeping data center power costs off your bill; the CPUC still has to write the actual tariff rules, due by January 1, 2028, so there is no bill impact yet.

no figure yet
TVA data center rate class proposal Tennessee Valley Authority, TN
Approved Supply and capacity price From Oct 2026

This does not change your bill directly; it applies a new charge to large new data center customers starting October 2026, which TVA says protects other customers from those costs.

no figure yet
Settled Base rate case

AES Ohio settled for a much smaller increase than it first asked for, about 2.43 dollars a month in year one instead of the original double digit request, but the Public Utilities Commission of Ohio still has to vote on it.

+$2a month
On bills now Rate matter

The large load rate is meant to make data centers and other big new customers cover the cost of the power plants and lines built to serve them, rather than spreading that cost across residential bills.

no figure yet
MLGW rate increase (xAI context) Memphis Light, Gas and Water, TN
On bills now Base rate case

MLGW is a municipal utility that buys its power from TVA, so its base rates are set by Memphis City Council rather than a state commission, and large customers like xAI are billed under MLGW's own commercial and industrial rate schedules, separate from residential rates.

+$5a month
On bills now Rate matter

A May 2026 Earthjustice analysis estimated Mississippi households had already paid roughly 38 million dollars for transmission and other infrastructure connected to the AWS project as of that point, though Entergy disputes how that cost should be characterized.

no figure yet
On bills now Statewide From Aug 2026

This new law is meant to stop the cost of big new electricity users like data centers from landing on ordinary residential bills, rather than raising bills directly.

no figure yet
Approved Rider or surcharge Decided Aug 1, 2026

This is a structural change in who pays for data center grid buildout rather than a simple rate increase. The new GS-5 class and the direct-connect tariff are both designed to keep those costs on the data centers.

+$0.94a month
On bills now Rider or surcharge From Jul 2026

This decision is why your PGE bill went slightly down in mid 2026; it shifted data center costs off residential rates.

-$2a month, est.
Settled Base rate case From Jul 2026

A typical PPL residential customer's total monthly bill was set to rise by a few dollars once the new distribution rates took effect July 1, 2026, on top of separate increases in the supply portion of the bill.

+$9a month, est.
On bills now Supply and capacity price From Jul 2026

If you do not shop for a competitive electricity supplier, the default generation portion of your DC Pepco bill went up about 9.56 dollars a month starting July 2026 because of higher regional power auction prices.

+$10a month
Approved Rate matter Decided Jun 17, 2026

This approved contract is designed to have Amazon's data centers pay their own way, with savings passed to other NIPSCO customers as bill credits rather than costs.

no figure yet
On bills now Supply and capacity price From Jun 2026

Capacity costs baked into the summer supply price are the main channel through which data center growth is already raising Ameren Illinois electric bills.

no figure yet
On bills now Supply and capacity price From Jun 2026

A PECO household that buys its generation supply from PECO rather than a competitive shopper saw its supply charge rise by about 5 percent starting with its June 2026 bill.

+$7a month, est.
Approved Statewide Decided Apr 30, 2026

This does not change anyone's electric rate directly, but it is meant to stop the cost of new substations and power lines built for data centers from being added to everyone else's bill.

no figure yet
Approved Supply and capacity price Decided Apr 24, 2026

This tariff does not change home electric rates by itself, but it is meant to make large new data centers pay the full cost of the power plants and lines built to serve them instead of spreading those costs across everyone's bill.

no figure yet
Approved Supply and capacity price Decided Dec 19, 2025

The December 2025 certification of about 9,885 MW of new generation for data center load came with a promise of at least $8.50 a month of downward pressure on a typical bill in 2029 through 2031, because large customers are meant to carry more of the cost. Consumer groups warned it could instead add around $20 a month if the projected data center demand does not show up.

no figure yet
Approved Rate matter Decided Dec 3, 2025

This is a service contract, not a residential rate change. The protections in it exist to keep the cost of serving the data center from shifting onto Tucson homes; whether they hold is the thing to watch in TEP's future rate cases.

no figure yet
Settled Base rate case

If the commission approves the settlement as negotiated, a typical 1,000 kWh residential bill would rise about 6.53 dollars a month once new rates take effect; the case is not yet decided.

+$7a month
Settled Base rate case

A North Carolina Utilities Commission ruling on this case is due by September 20, 2026; if it does not rule in time, Duke's full 18.1 percent original request takes effect instead of the smaller settlement figure.

+$16a month
Approved Supply and capacity price Decided Nov 6, 2025

This does not change a typical home bill by itself, but it sets the rules meant to stop the cost of new data center power hookups from being spread across every Consumers Energy customer's rate.

no figure yet
Approved Rate matter, gas Decided Aug 29, 2025

Watch for how the Louisiana Public Service Commission enforces cost sharing if Meta's actual power use ever falls short of what was promised, since that is what determines whether these plants ever show up on a typical household bill.

no figure yet
Approved Supply and capacity price Decided Jul 9, 2025

This is a minimum bill requirement for very large new customers, not a rate change for homes, but it exists specifically to keep data center grid costs off residential bills.

no figure yet
On bills now Base rate case From Jul 2025

Data center growth on Entergy Mississippi's system is being credited with keeping your bill roughly flat instead of rising, according to the company; Mississippi bills remain about 20 percent below the national average.

-$0.04a month
On bills now Rate matter From Jun 2025

This applies statewide in the ERCOT region, not just Oncor territory. It does not change a bill directly; it decides whether data center grid costs land on developers or on the delivery rates everyone pays.

no figure yet
On bills now Supply and capacity price From Jun 2025

This is the single biggest reason ComEd bills jumped in summer 2025 and again in 2026, and PJM and consumer groups both tie it directly to data center demand growth.

+$11a month
JCP&L Basic Generation Service price jump, June 2025 JCP&L (Jersey Central Power and Light), NJ
On bills now Supply and capacity price From Jun 2025

This is a default electric supply price increase from the statewide auction, not a JCP&L delivery rate case; shopping for a competitive supplier avoids it.

+$26a month, est.
PSE&G Basic Generation Service price jump, June 2025 Public Service Electric and Gas, NJ
On bills now Supply and capacity price From Jun 2025

If you buy default electric supply through PSE&G rather than a third-party supplier, this auction result is why your total bill jumped in mid-2025; it is a supply cost, not a PSE&G delivery rate increase.

+$22a month, est.
Approved Supply and capacity price Decided Feb 20, 2025

This deal is meant to keep the cost of new substations and transmission lines for AWS's data centers off the bills of regular I&M customers by making the data center pay for capacity it reserves, not just power it actually uses.

no figure yet
On bills now Rider or surcharge From Feb 2025

Since February 2025, new loads of 100 MW or more must sign custom contracts of up to 15 years with financial guarantees and minimum bills, which is the rule meant to keep data center grid costs off residential rates.

no figure yet
On bills now Rate matter From Jan 2025

This does not change anyone's electric bill by itself; it is a state sales tax break for data center owners, separate from the MPSC cases that set how those same data centers pay for electricity. It applies statewide, regardless of which utility serves the site.

no figure yet