This is a separate North Carolina case from Dominion's larger Virginia rate filings; it only affects Dominion customers in Dominion's small northeastern North Carolina service area.
Dominion Energy Virginia, Virginia
Data center cost allocation and transmission rider
Approved Rider or surcharge, docket PUR-2026-00056 before the Virginia State Corporation Commission.
As published by the utility or the commission.
What happens next
The decision is final; the new rate takes effect once the order sets a date. How rate cases work.
What it means for your bill
$
The commission reallocated the cost of substations and transmission lines built specifically to serve data centers. The rider as filed would have added about 2.90 dollars a month to a 1,000 kWh residential bill; the revised allocation cut that to about 0.94 dollars. The commission also ordered Dominion to file a formal tariff within 90 days governing who pays for direct-connect infrastructure going forward.
What it means for your bill: This is a structural change in who pays for data center grid buildout rather than a simple rate increase. The new GS-5 class and the direct-connect tariff are both designed to keep those costs on the data centers.
- Status
- Approved
- Utility
- Dominion Energy Virginia
- Commission
- Virginia State Corporation Commission
- Docket
- PUR-2026-00056
- Typical bill change
- +$0.94 a month
- Decided
- August 1, 2026
- Data center linked
- Yes. The filing ties part of the cost or the tariff design to data center load. The projects themselves: isadatacentercoming.com.
- Last checked
- August 29, 2026
Common questions
How much will my Dominion Energy Virginia bill go up?
Adds about $0.94 a month on a typical bill. As published by the utility or the commission.
When would the new rates start?
Not yet set. That is decided along with the case, usually as part of the commission's final order.
When is the hearing?
No hearing date is on record for this case.
How do I comment?
The comment period closed once this case was decided; its result is above.
Sources
- SCC orders Dominion to develop tariff to assign more transmission costs to data centers, Virginia Mercury, 2026-08-05
- Virginia Energy Regulatory Updates (June 2026), ReisingerGooch, 2026-06-01
Get an email when this changes
One email when a rate case is filed, gets a hearing date, or is decided for Dominion Energy Virginia. Nothing else.
Unsubscribe with one click. We do not sell the list.