This is a structural change in who pays for data center grid buildout rather than a simple rate increase. The new GS-5 class and the direct-connect tariff are both designed to keep those costs on the data centers.
Dominion Energy Virginia, Virginia
Deferred fuel cost recovery
Pending Fuel cost adjustment, docket PUR-2026-00078 before the Virginia State Corporation Commission.
As published by the utility or the commission.
Dominion's fuel and purchased power costs ran roughly a billion dollars past what bills collected. Recovering it directly would add about 21.79 dollars a month to a 1,000 kWh bill; Dominion proposes spreading it over 7 to 10 years with bonds instead, about 8 dollars a month. The hearing was August 12, 2026 and a decision is due by late September 2026.
- Status
- Pending
- Utility
- Dominion Energy Virginia
- Commission
- Virginia State Corporation Commission
- Docket
- PUR-2026-00078
- Typical bill change
- +$8.00 a month
- Last checked
- August 29, 2026
How to comment
The Virginia State Corporation Commission accepts written comments on the docket while the case is open, and holds public hearings on major cases. Commission site. Virginia Attorney General, Division of Consumer Counsel represents households in this case.
Sources
- Dominion asks SCC to recover an additional $922 million for fuel costs over multiple years, Henrico Citizen (Virginia Mercury), 2026-08-13
- Virginia Energy Regulatory Updates (June 2026), ReisingerGooch, 2026-06-01
Get an email when this changes
One email when a rate case is filed, gets a hearing date, or is decided for Dominion Energy Virginia. Nothing else.
Unsubscribe with one click. We do not sell the list.