Will My Bill Go Up

Indiana Michigan Power, Indiana

Indiana Michigan Power large load settlement (New Carlisle AWS)

Approved Supply and capacity price before the Indiana Utility Regulatory Commission.

No residential dollar figure published yet

The filing does not state a typical-bill impact we can verify. We will add one when the commission staff or the consumer advocate publishes it.

Fileddate not published
Hearingheld or waived
DecisionFeb 20, 2025
On billsdate not published

After Amazon Web Services announced an 11 billion dollar data center campus near New Carlisle, Indiana, Indiana Michigan Power reached a settlement with AWS, Microsoft, Google, the state consumer counselor and the Data Center Coalition on how large new customers pay for the grid upgrades they require. The Indiana Utility Regulatory Commission approved the deal on February 20, 2025. It requires a 12 year minimum contract, requires large customers to pay for at least 80 percent of their reserved capacity whether they use it or not, and sets an exit fee that can exceed 1 billion dollars for a 1 gigawatt customer that leaves early.

What it means for your bill: This deal is meant to keep the cost of new substations and transmission lines for AWS's data centers off the bills of regular I&M customers by making the data center pay for capacity it reserves, not just power it actually uses.

Status
Approved
Utility
Indiana Michigan Power
Commission
Indiana Utility Regulatory Commission
Decided
February 20, 2025
Data center linked
Yes. The filing ties part of the cost or the tariff design to data center load.
Last checked
August 29, 2026

Sources

Get an email when this changes

One email when a rate case is filed, gets a hearing date, or is decided for Indiana Michigan Power. Nothing else.

Unsubscribe with one click. We do not sell the list.

Other Indiana Michigan Power matters