Will My Bill Go Up

Tucson Electric Power, Arizona

Project Blue data center energy service agreement

Approved Rate matter before the Arizona Corporation Commission.

No residential dollar figure published yet

The filing does not state a typical-bill impact we can verify. We will add one when the commission staff or the consumer advocate publishes it.

Fileddate not published
Hearingheld or waived
DecisionDec 3, 2025
On billsdate not published

The Arizona Corporation Commission approved TEP's contract to serve the 286 MW Project Blue data center near Tucson on a 4 to 1 vote in December 2025, over two hours of public opposition centered on water use. TEP says the data center pays the standard largest-customer rate with minimum bills and termination fees so the buildout cost stays off residential bills.

What it means for your bill: This is a service contract, not a residential rate change. The protections in it exist to keep the cost of serving the data center from shifting onto Tucson homes; whether they hold is the thing to watch in TEP's future rate cases.

Status
Approved
Utility
Tucson Electric Power
Commission
Arizona Corporation Commission
Decided
December 3, 2025
Data center linked
Yes. The filing ties part of the cost or the tariff design to data center load.
Last checked
August 29, 2026

Sources

Get an email when this changes

One email when a rate case is filed, gets a hearing date, or is decided for Tucson Electric Power. Nothing else.

Unsubscribe with one click. We do not sell the list.

Other Tucson Electric Power matters