This is a service contract, not a residential rate change. The protections in it exist to keep the cost of serving the data center from shifting onto Tucson homes; whether they hold is the thing to watch in TEP's future rate cases.
Tucson Electric Power, Arizona
2026 general rate case
Pending Base rate case, docket E-01933A-25-0103 before the Arizona Corporation Commission.
As published by the utility or the commission.
TEP is asking for about 11.6 percent more on residential bills, roughly 12.92 dollars a month at median usage. The attorney general's office argued in testimony that only about a 4 percent increase is justified. TEP says this case is unrelated to the Project Blue data center agreement; a decision could come before the end of 2026.
- Status
- Pending
- Utility
- Tucson Electric Power
- Commission
- Arizona Corporation Commission
- Docket
- E-01933A-25-0103
- Requested
- 11.6% residential
- Typical bill change
- +$12.92 a month
- Last checked
- August 29, 2026
How to comment
The Arizona Corporation Commission accepts written comments on the docket while the case is open, and holds public hearings on major cases. Commission site. Residential Utility Consumer Office represents households in this case.
Sources
- TEP 2026 Rate Review, Tucson Electric Power, 2026-08-19
- TEP Rate Case Timeline Update, Arizona Corporation Commission, 2026-02-17
Get an email when this changes
One email when a rate case is filed, gets a hearing date, or is decided for Tucson Electric Power. Nothing else.