Pending rate cases in Ohio
Ranked by what each would add to a typical monthly bill if approved as asked. Commissions usually approve less. Cases without a published residential figure sit at the end.
This is a separate, newer AES Ohio rate request from the company's 2024 case; it proposes distribution charge increases stretching from 2027 through 2029, and PUCO staff has recommended cutting the company's ask by roughly a third.
Recent decisions
FirstEnergy asked for a much bigger increase than PUCO approved; do not assume the 13.02 dollar figure the company originally cited is what actually landed on bills.
FirstEnergy asked for a much bigger increase than PUCO approved; do not assume the 2.99 dollar figure the company originally cited is what actually landed on bills.
FirstEnergy asked for a much bigger increase than PUCO approved; do not assume the 1.56 dollar figure the company originally cited is what actually landed on bills.
A typical residential customer using 1,000 kWh a month gets about 65.61 dollars in bill credits spread over three months from this settlement, separate from any base rate case.
This is a minimum bill requirement for very large new customers, not a rate change for homes, but it exists specifically to keep data center grid costs off residential bills.