Will My Bill Go Up

Tracker

Pending rate cases in Arizona

Ranked by what each would add to a typical monthly bill if approved as asked. Commissions usually approve less. Cases without a published residential figure sit at the end.

Recent decisions

Approved Rate matter Decided Dec 3, 2025

This is a service contract, not a residential rate change. The protections in it exist to keep the cost of serving the data center from shifting onto Tucson homes; whether they hold is the thing to watch in TEP's future rate cases.

no figure yet
FY2026 price plan change Salt River Project, AZ
On bills now Rate matter From Nov 2025

SRP is a public power district whose rates are set by its own elected board, not the Arizona Corporation Commission, so rate changes come through board votes rather than commission dockets.

+$6a month