This is a small, gradually rising charge if approved: about a quarter a month at first, growing to under a dollar a month over a few years; it has not been decided yet.
Tracker
Pending rate cases in Arkansas
Ranked by what each would add to a typical monthly bill if approved as asked. Commissions usually approve less; here is how much less, measured. Cases without a published residential figure sit at the end. See what changed recently across every case we track.
Coming up
Dates on the record. Comment deadlines are the ones you can act on.
- Dec 1 Duke Energy Ohio: Duke Energy Ohio distribution rate case (hearing)
- Dec 1 Portland General Electric: General rate case for 2027 rates (comment deadline)
- Dec 1 Potomac Edison: Potomac Edison Maryland reliability rate case (hearing)
- Dec 7 Southwest Gas: Southwest Gas Arizona general rate case (hearing)
- Dec 16 Entergy Louisiana: Entergy Louisiana's second Meta gas plant expansion (hearing)
- Dec 18 Potomac Edison: Potomac Edison Maryland reliability rate case (comment deadline)
- Dec 23 Baltimore Gas and Electric: BGE 2027-2029 electric rate case (comment deadline)
This case is about batteries built to serve a Google data center; Entergy's filings say Google, not other customers, is expected to cover most of the cost, but the commission has not yet decided the case.
Recent decisions
A settlement reached by Entergy Arkansas and commission staff calls for no base rate increase for residential customers in this case, but the Arkansas Public Service Commission has not yet issued a final order approving it.
Your Entergy Arkansas bill went up about 6.08 dollars a month starting January 2026 through the utility's annual formula rate plan adjustment.
Get the decision in your inbox
Pick your state and we email you when a rate case there is filed, gets a hearing date, or is decided. Nothing else.
Unsubscribe with one click. We do not sell the list.
Need statewide alerts, exports or a hearing calendar for work? Email [email protected] and say what you need.