This pending case would raise Entergy Texas delivery rates significantly; it has not been decided.
Tracker
Pending rate cases in Texas
Ranked by what each would add to a typical monthly bill if approved as asked. Commissions usually approve less; here is how much less, measured. Cases without a published residential figure sit at the end. See what changed recently across every case we track.
Coming up
Dates on the record. Comment deadlines are the ones you can act on.
- Dec 1 Duke Energy Ohio: Duke Energy Ohio distribution rate case (hearing)
- Dec 1 Portland General Electric: General rate case for 2027 rates (comment deadline)
- Dec 1 Potomac Edison: Potomac Edison Maryland reliability rate case (hearing)
- Dec 7 Southwest Gas: Southwest Gas Arizona general rate case (hearing)
- Dec 16 Entergy Louisiana: Entergy Louisiana's second Meta gas plant expansion (hearing)
- Dec 18 Potomac Edison: Potomac Edison Maryland reliability rate case (comment deadline)
- Dec 23 Baltimore Gas and Electric: BGE 2027-2029 electric rate case (comment deadline)
Recent decisions
In most of Texas you buy electricity from a retail provider you choose; Oncor only charges for delivery. These figures cover the delivery part of the bill that everyone pays.
This applies statewide in the ERCOT region, not just Oncor territory. It does not change a bill directly; it decides whether data center grid costs land on developers or on the delivery rates everyone pays.
Get the decision in your inbox
Pick your state and we email you when a rate case there is filed, gets a hearing date, or is decided. Nothing else.
Unsubscribe with one click. We do not sell the list.
Need statewide alerts, exports or a hearing calendar for work? Email [email protected] and say what you need.