Will My Bill Go Up

Tracker

Pending rate cases in Indiana

Ranked by what each would add to a typical monthly bill if approved as asked. Commissions usually approve less; here is how much less, measured. Cases without a published residential figure sit at the end. See what changed recently across every case we track.

Coming up

Dates on the record. Comment deadlines are the ones you can act on.

1
Pending Base rate case

This is a proposed decrease, not an increase; I&M says new large industrial and data center customers are helping pay for the grid, letting it lower rates for everyone else, but the case still needs IURC approval.

-$7a month, est.

Recent decisions

Approved Rate matter Decided Jun 17, 2026

This approved contract is designed to have Amazon's data centers pay their own way, with savings passed to other NIPSCO customers as bill credits rather than costs.

no figure yet
Approved Supply and capacity price Decided Feb 20, 2025

This deal is meant to keep the cost of new substations and transmission lines for AWS's data centers off the bills of regular I&M customers by making the data center pay for capacity it reserves, not just power it actually uses.

no figure yet

Get the decision in your inbox

Pick your state and we email you when a rate case there is filed, gets a hearing date, or is decided. Nothing else.

Unsubscribe with one click. We do not sell the list.

Need statewide alerts, exports or a hearing calendar for work? Email [email protected] and say what you need.