This is Evergy's opening ask for its Kansas City area customers; the company already cut it once because of new data center revenue, and the final number could move further as the case proceeds.
Tracker
Pending rate cases in Missouri
Ranked by what each would add to a typical monthly bill if approved as asked. Commissions usually approve less. Cases without a published residential figure sit at the end.
All states
AZ (2)
AR (1)
CA (3)
CO (2)
CT (1)
DE (1)
GA (2)
HI (1)
ID (1)
IN (2)
IA (1)
LA (1)
ME (1)
MD (1)
MA (1)
MI (2)
MO (2)
NV (2)
NJ (1)
NY (4)
OH (2)
OR (2)
SD (1)
TN (1)
TX (1)
UT (1)
VA (2)
WA (4)
WI (3)
WY (1)
1
Evergy Missouri Metro rate case
Evergy Metro, MO
+$18a month
2
Ameren Missouri new base rate case, 2026-2027
Union Electric, MO
This new Ameren Missouri request follows closely on the heels of the case approved in April 2025; nothing has been decided yet.
+$13a month
Recent decisions
Ameren Missouri base rate case
Union Electric, MO
The final Ameren Missouri increase approved in April 2025 was smaller than the 17.45 dollar figure the company originally requested, and the monthly customer charge did not go up.
+$20a month, est.
Evergy Missouri West base rate case
Evergy Missouri West, MO
This increase has been on Evergy Missouri West bills since the start of 2025.
+$8a month