BGE has asked to raise electric bills about 8.18 dollars a month starting in 2027, plus a separate 9 dollar a month Baltimore-City-only surcharge and a new voluntary prepaid FlexPay program that consumer advocates warn could increase disconnections. Nothing has been approved; a final order is due January 28, 2027.
Potomac Edison Maryland reliability rate case
Pending Base rate case, docket Case No. 9904 before the Maryland Public Service Commission.
5.3% of the average Maryland bill of $166 (EIA, 2024); your own bill scales with your usage. Our arithmetic, not the utility's figure; the methodology page shows how.
What happens next
Next comes a hearing on December 1, 2026, then a decision from the Maryland Public Service Commission. Many states give the commission a deadline of roughly seven to eleven months from filing. How rate cases work.
What it means for your bill
$
Potomac Edison, a FirstEnergy subsidiary, filed a new rate request with the Maryland Public Service Commission on September 4, 2026, now docketed as Case No. 9904, seeking 52.8 million dollars a year, about 5.3 percent more for a typical residential customer, to pay for grid reliability and modernization work including substation replacement, reconductoring and vegetation management. A virtual pre-hearing conference was held October 9, 2026; the commission has since scheduled public comment hearings for December 1, 2026 in Cumberland and December 8, 2026 virtually, with written comments due by December 18, 2026 and a final order expected around April 2027. No decision has been made.
What it means for your bill: If approved as filed, this would add roughly 5.3 percent to a typical Potomac Edison Maryland bill; nothing has been decided yet.
- Status
- Pending
- Utility
- Potomac Edison
- Commission
- Maryland Public Service Commission
- Docket
- Case No. 9904
- Filed
- September 4, 2026
- Requested
- 5.3% residential, $52.8 million a year
- Next hearing
- December 1, 2026
- Comment deadline
- December 18, 2026
- Last checked
- October 27, 2026
Common questions
How much will my Potomac Edison bill go up?
Would add about $9 a month on a typical bill. 5.3% of the average Maryland bill of $166 (EIA, 2024); your own bill scales with your usage.
When would the new rates start?
Not yet set. That is decided along with the case, usually as part of the commission's final order.
When is the hearing?
December 1, 2026.
How do I comment?
Attend a public comment hearing on Case No. 9904, in person December 1, 2026 at Allegany College of Maryland in Cumberland or virtually December 8, 2026, or file written comments with the Maryland Public Service Commission by December 18, 2026. Comment page.
How to comment
Attend a public comment hearing on Case No. 9904, in person December 1, 2026 at Allegany College of Maryland in Cumberland or virtually December 8, 2026, or file written comments with the Maryland Public Service Commission by December 18, 2026. Comment page. Office of People's Counsel represents households in this case.
History
- Oct 27, 2026: Hearing: December 1, 2026
- Oct 27, 2026: Comment deadline: December 18, 2026
- Sep 29, 2026: Hearing: October 9, 2026
- Sep 29, 2026: Comment deadline: October 7, 2026
- Sep 15, 2026: Added as pending
Sources
- Potomac Edison Proposes Rate Adjustment to Support Electric System Reliability, PR Newswire, 2026-09-04
- Potomac Edison seeks $52.8 million Maryland distribution revenue increase, Hoodline, 2026-09
- Upcoming Public Comment Hearings, Maryland Public Service Commission, 2026-10-27
Get an email when this changes
One email when a rate case is filed, gets a hearing date, or is decided for Potomac Edison. Nothing else.
Unsubscribe with one click. We do not sell the list.