Will My Bill Go Up

NV Energy (Nevada Power), Nevada

2026 fuel cost filings

Approved Fuel cost adjustment before the Public Utilities Commission of Nevada.

-$5a month
on a typical bill, as approved

As published by the utility or the commission.

What happens next

The new rate took effect October 1, 2026 and is already on your bill. How rate cases work.

What it means for your bill

$

Fileddate not published
Hearingheld or waived
Decisiondecided
On billsOct 1, 2026

NV Energy's annual deferred energy rate adjustment lowered southern Nevada (Nevada Power) electric bills by about 5.01 dollars a month, cutting about 100.2 million dollars in annual revenue, effective October 1, 2026, citing falling fuel and wholesale power costs. In northern Nevada (Sierra Pacific Power), the same filing cut electric bills about 1.86 dollars a month while raising natural gas bills about 1.01 dollars a month, also effective October 1, 2026.

Status
Approved
Utility
NV Energy (Nevada Power)
Commission
Public Utilities Commission of Nevada
Requested
-3.6% residential, $-100.2 million a year
Approved
-3.6% residential, $-100.2 million a year
Typical bill change
-$5.01 a month
On bills from
October 1, 2026
Last checked
October 27, 2026

Common questions

How much will my NV Energy (Nevada Power) bill go up?

Takes about $5 off a month on a typical bill. As published by the utility or the commission.

When would the new rates start?

They already did, on October 1, 2026.

When is the hearing?

No hearing date is on record for this case.

How do I comment?

The comment period closed once this case was decided; its result is above.

History

Sources

Get an email when this changes

One email when a rate case is filed, gets a hearing date, or is decided for NV Energy (Nevada Power). Nothing else.

Unsubscribe with one click. We do not sell the list.

Other NV Energy (Nevada Power) matters

Pending Rate matter

Nothing here changes a bill today. What matters is whether the large load contract survives intact; if it is weakened, the cost of plants built for data centers starts showing up in the next general rate cases around 2027 and 2028.

no figure yet

Other pending cases in Nevada

1
2026 resource plan and large load contract NV Energy (Nevada Power), NV
Pending Rate matter

Nothing here changes a bill today. What matters is whether the large load contract survives intact; if it is weakened, the cost of plants built for data centers starts showing up in the next general rate cases around 2027 and 2028.

no figure yet